What this tool does

Estimates the concrete for a poured retaining wall's stem and base from its length, height, thicknesses and base width, with wastage and cost.

Estimates the concrete volume and cost of a poured retaining wall's stem and base from its length, retained height, thicknesses and base width.

Inputs
ft
ft
in
in
ft
%
$
Result

Retaining Wall Concrete

4.93 yd³

Stem Volume
2.47 yd³
Base Volume
2.22 yd³
Total (+ wastage)
4.93 yd³
Estimated Cost
$812.78
⚠ Structural
Walls retaining more than about 4 ft (1.2 m) of soil generally need an engineer's design and a permit; check your local code

Diagram

20 ft5 ft
Price it on PlainEstimate

Opens these materials as a new estimate on PlainEstimate, our free estimate and invoice app.

Plain Estimate
From BrightScale Labs
Invoice maker
Quote at the door. Signed on the spot.
Estimates and invoices for trades, built while you are still in the room.
Scan to get
Get it onGoogle Play

People also use

Formula Used
V=(L⋅H⋅ts+L⋅wb⋅tb)(1+w)V = \left( L \cdot H \cdot t_s + L \cdot w_b \cdot t_b \right)(1 + w)
VV
Concrete volume
LL
Wall length
HH
Wall height
tst_s
Stem thickness
wbw_b
Base width
tbt_b
Base thickness
ww
Wastage allowance (decimal)

How the retaining wall calculator works

A poured cantilever retaining wall has two parts: a vertical stem that holds the soil and a base slab that carries the load and resists tipping. The concrete is the volume of each. This calculator works out the stem as length × height × stem thickness, the base as length × base width × base thickness, adds them, applies your wastage and prices the result. The formula is V = (L × H × t_s + L × w_b × t_b) × (1 + w). The page works in feet and inches, with the volume in cubic yards, and converts internally, so the metric and US-unit versions agree.

Example with the defaults on this page: a wall 20 ft long that retains 5 ft of soil, with an 8 in stem, a 12 in base and a 3 ft base width. The stem is 20 × 5 × (8 ÷ 12) = 66.7 ft³. The base is 20 × 3 × (12 ÷ 12) = 60 ft³. Together that is 126.7 ft³, and with 5% wastage it is 133.0 ft³, which is 4.93 yd³ or 3.77 m³. At $165 a cubic yard the concrete costs $812.78. The concrete weighs about 20,000 lb (10 tons), at about 150 lb/ft³.

Height and base width drive the quantity. Raising the wall to 8 ft, with a 10 in stem, a 16 in base and a 5 ft base width, takes the same 20 ft wall to 266.7 ft³, which is 9.88 yd³ before wastage, so about twice the concrete for a wall 60% taller. Stem volume grows with height, and the base is usually made wider as the wall gets taller.

Typical US masonry and brickwork wastage

The tool defaults to 5% wastage and lets you change it. Concrete for a wall goes into a trench and formwork that are never exactly the planned shape. The trench is a little over, the forms bow under the weight of the concrete, and some is lost to spillage, so many contractors use 5 to 10%. That is a trade habit and not a published standard. On the first example, 5% is about 0.23 yd³. Order the concrete by the cubic yard, and ask the supplier about a short last load.

The tool counts only the stem and the base as rectangles. A tapered stem, a shear key under the base, steps along a sloping site and corners are not counted, and they change the volume by a few percent. Take the dimensions from the drawing, not from a guess.

What this tool does not do

It does not design the wall. The stem and base thickness, the width of the base and the reinforcement depend on the height of soil, the soil type, the slope above, any load on top, and water. It does not include reinforcement, drainage, backfill, formwork or excavation. It does not count blocks for a segmental wall, so for a block wall use a block calculator. It does not work out the wall's stability against sliding, tipping or bearing, and it cannot say whether a wall is safe.

On-site considerations for retaining wall

Water is the main enemy of a retaining wall. Soil behind a wall that fills with water pushes much harder, and walls fail when drainage is missing. A wall needs a free-draining backfill, a drain at the base that carries water away, and weep holes or a drain where the design calls for them. Keep the surface water from the slope above away from the wall. Compact the backfill in layers, and use light equipment near the wall, because heavy rollers can load it.

The excavation for the base can be deep, and a trench in unstable soil can collapse. HSE guidance for Great Britain treats any trench as a collapse risk and recommends support or battering, and similar rules apply elsewhere. Call the local utility locating service before you dig, and keep the base on firm ground below the frost line where it applies. Steel reinforcement, set on chairs at the right cover, is common in a poured wall, and it comes from the design.

Codes and compliance

In the United States the International Residential Code does not set the size of most retaining walls, and walls above about 4 ft of retained soil, or with a surcharge, are generally designed by an engineer and need a permit. ACI 318 covers structural concrete, and the National Concrete Masonry Association publishes guidance on segmental walls. A wall near a boundary, a slope, a building or a road is more likely to need approval. Do not build a retaining wall on a neighbour's land without agreement, and check that the wall will not change drainage onto their property. Wet concrete burns skin and eyes, so wear gloves, boots and eye protection. Other countries have their own rules, so follow the ones where you build.

Before you order

Get the dimensions from the design, with the stem, base and any shear key or taper. Work out the concrete volume, add your margin, and ask the supplier about the mix, the access for a truck or a pump, and the delivery time. Check that you have the formwork, reinforcement, drainage and backfill ready before the concrete arrives. Compare the delivered price per cubic yard, not the price per truck, and ask about a short-load charge. Plan how you will place and vibrate the concrete, and how you will cure it.

Adjusting the defaults

Every input is editable. The length, height, thicknesses and base width must be above zero, and the wastage must be zero or more. A blank or zero field is refused instead of silently using a default, and a blank price hides the cost line. For a wall of different heights along its length, split it into sections, and run the tool for each. For a stepped base, run it for each step.

Using this retaining wall calculator alongside other BuildMetricLab tools

Pair this estimate with the rebar calculator for the reinforcement, the ready-mix truck calculator for delivery, and the gravel calculator for the drainage stone behind the wall. All BuildMetricLab tools run in your browser. Nothing you type is sent anywhere, and every formula is shown on the page so you can audit the maths.

Sources & methodology

Concrete volume = (length × height × stem thickness + length × base width × base thickness) × (1 + wastage ÷ 100). The stem is the vertical wall and the base is the footing slab, so the height is measured from the top of the base. The page takes ft and inches and gives cubic yards (1 yd³ = 27 ft³ = 0.7646 m³). Cost = volume × price per unit volume, hidden if no price is entered. The length, height, thicknesses and base width must be above zero, the wastage zero or more and the price zero or more. The tool assumes a rectangular stem and base with constant thickness, so a tapered stem, a shear key, a toe or heel of different size and steps are not counted. It does not include reinforcement, drainage, backfill, formwork or excavation, and it does not design the wall.

Frequently asked questions

Are retaining wall calculator results accurate enough to order materials?

They are a good first quantity for the concrete in a poured wall of the dimensions you enter, and nothing more. The tool counts the stem and the base, and ignores steps, a shear key, battered faces, returns and footings that vary. Reinforcement, drainage stone and backfill are separate and not included. Take the dimensions from the design or the engineer's drawing, and confirm the volume with your supplier.

What wastage percentage should I use?

The default is 5%. Concrete is placed into trenches and forms that are never exactly the planned shape, so many contractors use 5 to 10%. That is a trade habit and not a published standard. Enter 0 for none. For the default 20 ft wall, 5% extra is about 0.23 yd³.

Does this tool replace professional design advice?

No. A retaining wall's size comes from the height of the soil, the soil type, the slope above, anything built on it, and water. This tool does not check any of those. Walls retaining more than about 4 ft (1.2 m) of soil, or carrying a surcharge, usually need an engineer's design and a permit. Consult a licensed contractor or engineer.

Can I change the unit prices?

Yes. The price per cubic yard is editable, and a blank price hides the cost line. A price of zero is accepted. The length, height, thicknesses and base width must be above zero, and the wastage must be zero or more.