Excavation volume in place and loose, loads to remove, and weight from the hole size, the bulking factor and the soil density

Updated October 9, 2026 · Live

What this tool does

Works out the bank volume of a rectangular excavation, the loose volume it becomes once dug using a bulking factor, the number of skips or dumpsters of your size needed to remove it, the total weight at the in-place density and the weight of one full container. Shows every figure in cubic metres and cubic yards, tonnes and US tons.

Length times width times depth, times the bulking factor for loose volume, divided by the container size for loads.

Inputs
ft
ft
ft
×
lb/ft³
yd³
Result

Excavation Volume (in place)

26.22 yd³

Excavation
33.0 × 6.5 × 3.3 ft
Bank Volume (in place)
26.22 yd³ (20.04 m³)
Loose Volume (× 1.25 bulking)
32.77 yd³ (25.06 m³)
10 yd³ Loads to Remove
4
Weight at 1.60 t/m³ in place
35.39 US tons (32.11 t)
Weight of One Full Load
10.80 US tons (9.80 t)
Before Digging
Locate buried services first; support, batter or step any face people will work beside

Diagram

33 ft6.5 ft3.3 ft
Plain Estimate
From BrightScale Labs
Invoice maker
Quote at the door. Signed on the spot.
Estimates and invoices for trades, built while you are still in the room.
Scan to get
Get it onGoogle Play

What this tool does not check

  • Does not check buried services — use a CAT scan and "dial before you dig" (LSBUD).
  • Does not size sheet piling or trench support — deep trenches need engineered shoring.
  • Does not account for contaminated soil disposal costs.
  • Does not serve Party Wall notices when excavating near a boundary.

People also use

Formula Used
Vb=L⋅W⋅D,Vl=Vb⋅k,N=⌈VlS⌉V_b = L \cdot W \cdot D, \quad V_l = V_b \cdot k, \quad N = \left\lceil \frac{V_l}{S} \right\rceil
VbV_b
Bank (in-place) volume
VlV_l
Loose volume to remove
NN
Loads
LL
Length (ft)
WW
Width (ft)
DD
Depth (ft)
kk
Bulking factor, bank to loose
SS
Container size (yd³)

How the excavation volume calculator works

Dug ground takes up more room than it did in the hole. The calculator starts with the hole, length by width by depth, which is the bank or in-place volume that a contractor prices the digging on, and then multiplies by a bulking factor to get the loose volume that goes into skips or dumpsters. The US Army's FM 5-434, Earthmoving Operations gives the factors in its Table 1-1: bank to loose is 1.11 for sand or gravel, 1.25 for loam (common earth), 1.43 for clay and 1.50 for blasted rock, and the text beside its Table 1-2 explains the idea with dry clay, which swells 40 percent, "which means that 1 cubic yard of clay in the bank state will fill a space of 1.4 cubic yards in a loosened state". The British Geological Survey publishes a bulking dataset for the soils and rocks of Great Britain on the same principle. The loose volume divided by the container size, rounded up, is the number of loads.

The weight rows are the other half of the answer, because soil fills a container by weight long before it fills it by volume. The bank volume times the in-place density gives the total weight; the Health and Safety Executive's excavations page (UK) puts it simply: "depending on conditions, a cubic metre of soil can weigh in excess of 1.5 tonnes". FM 5-434 Table 1-2 gives bank weights of 2,180 to 2,980 lb per cubic yard for dry earth, 3,500 to 4,000 wet, 2,360 to 2,780 for dry clay and 3,360 to 4,200 wet, which is 1.3 to 2.5 t/m³. The default is 1.6 t/m³ (100 lb/ft³, 2,700 lb/yd³), inside the dry-earth range. The Weight of One Full Load row is the container volume, un-bulked back to bank volume, times the density: what a container actually carries when it is full of this ground.

The US default is a 33 ft by 6.5 ft by 3.3 ft footing trench: 26.22 yd³ (20.04 m³) in place, 32.77 yd³ loose at 1.25, so four 10 yd³ dumpsters, weighing 35.4 US tons (32.1 t) in all and 10.8 US tons per full dumpster. The metric default is 10 m by 2 m by 1 m: 20.00 m³ in place, 25.00 m³ loose, five 6 m³ skips, 32.0 t in all and 7.68 t per full skip.

Typical US drainage and earthworks wastage

Bulking is not waste, but it is the allowance that decides the haulage, and the factor is the thing to get right. FM 5-434 Table 1-2 gives swell of 10 to 15 percent for sand and gravel, 15 to 35 percent for dry earth and 25 for wet, 40 for clay, 50 for trap rock and 65 for shale, and notes that these "are averages for common materials" that "vary with such factors as grain size, moisture content, and degree of compaction". Topsoil and made ground are usually taken at the loam figure; a stiff clay dug in lumps goes to 1.4 or more; sand and gravel bulk least, at 10 to 15 percent. Where the ground will be reused on site, the compacted volume is smaller again than the bank volume, 0.90 for sand and gravel and 0.72 for clay in Table 1-1, which is why backfill never quite goes back in the hole.

Container weight limits are the second allowance. In the UK, ISM Waste's skip size guide notes that "a 6 yard skip is the largest skip that can be filled entirely with heavy waste such as soil, rubble, and bricks", and that large skips are not suitable for large quantities of soil; a 6-yard skip is 4.6 m³, so at 1.6 t/m³ in place and 1.25 bulking a full one holds 5.9 t. In the United States, Dumpsters.com gives a 10 yd³ dumpster a typical limit of 1 to 2 tons and a heavy-debris dumpster of the same size up to 10 tons; the default trench puts 10.8 US tons in a full 10 yd³ container, so it is the heavy-debris service or part loads. Enter the container you will be given, and compare the Weight of One Full Load row with its limit.

What this tool does not do

It works on a rectangular hole with vertical sides. A battered or stepped excavation, which is what a deep one has to be for safety, holds more than length by width by depth; dig the trapezoid as two rectangles or use the average width. It does not take off the volume of a foundation, pipe or bedding that goes back in, nor count the material kept on site for backfill or landscaping, which should be subtracted from the loads before ordering skips. It does not price the haulage or the tipping, which in the UK is charged by weight and by waste classification, and it does not know whether the ground is contaminated or whether an archaeological condition applies.

On-site considerations for excavation volume

Depth is the figure that changes how the hole is dug, not just how much comes out. In the United States, OSHA 29 CFR 1926.652 requires a protective system, sloping, benching, shoring or a shield, for anyone in an excavation unless it is in stable rock or is "less than 5 feet (1.52 m) in depth and examination of the ground by a competent person provides no indication of a potential cave-in". In the UK there is no depth threshold at all: the HSE's construction information sheet 64 says "don't assume ground will stand unsupported" and to "shore, step or batter back", and the HSE page adds that "no ground can be relied upon to stand unsupported in all circumstances". A battered side adds volume, which is the first thing to put back into the calculator once the method is known.

Buried services come before the first bucket. In the United States 811 is "the free national before-you-dig service"; contact it "a few business days before you begin any digging" and wait for every utility to respond. In the UK the HSE page lists the location of existing services among the information to be gathered and used in planning the excavation, and damage to buried electricity cables and gas pipes is one of the accidents it is written to prevent. Spoil stacked beside the trench loads its sides, so the loose volume is also the pile that has to go somewhere safe on the day.

Codes and compliance

What the soil is decides where it can go. In the UK, excavated soil is generally treated as waste once it leaves the site, and skip companies price clean soil, soil with rubble and contaminated soil differently; the hirer is responsible for describing it correctly. In the United States clean fill can often be reused or given away, while soil from a site with a history goes to a facility that will take it. Neither the bulking factor nor the weight changes that, but the weight row is what the tipping charge is based on.

Before you order

Skips in the UK are named in cubic yards, 6-yard, 8-yard and 12-yard, so convert before entering: 6 yards is 4.6 m³ and 8 yards is 6.1 m³. US dumpsters are 10, 20, 30 and 40 yd³, and the heavy-debris service with the higher weight limit is usually offered only in the smaller sizes. The load count is for the container you can actually get, and if the Weight of One Full Load row is above that container's limit, the hirer will fill it part way and the count goes up in proportion.

Adjusting the defaults

Every input is editable. Length, width and depth are the hole as dug, in feet or metres. The bulking factor runs from 1.0 to 1.6, with the FM 5-434 figures in the tooltip. Density is the in-place weight of the ground, in lb/ft³ or t/m³. The container size is the skip or dumpster you will be given, in yd³ or m³, and the loads round up.

Using this excavation volume calculator alongside other BuildMetricLab tools

Choose the container with the dumpster size calculator, size the stone that goes back into the hole with the crushed stone base calculator, and a soakaway with the dry well calculator. All BuildMetricLab tools run in your browser with no sign-up, and the formula is on the page so the maths can be checked.

Sources & methodology

Bank volume = length × width × depth; loose volume = bank × bulking factor; loads = loose ÷ container size, rounded up; weight = bank × in-place density; weight of one full load = (container ÷ bulking factor) × density. US inputs are converted first: ft × 0.3048 to m, yd³ × 0.7646 to m³, lb/ft³ × 0.01602 to t/m³; 1 t = 1.1023 US tons. Factors from FM 5-434 Table 1-1 (bank to loose): sand or gravel 1.11, loam 1.25, clay 1.43, rock 1.50; Table 1-2 swell: sand and gravel 10 to 15%, dry earth 15 to 35%, wet earth 25%, clay 40%, trap rock 50%, shale 65%; bank weights dry earth 2,180 to 2,980 lb/yd³, wet earth 3,500 to 4,000, dry clay 2,360 to 2,780, wet clay 3,360 to 4,200. Default density 1.6 t/m³ (100 lb/ft³).

Frequently asked questions

Are excavation volume calculator results accurate enough to order materials?

Yes, for a rectangular hole with vertical sides. The bank volume is what the digging is priced on, the loose volume is what the skips or dumpsters hold, and the weight is what the tipping is charged on. The things to check before ordering are the bulking factor for your ground, whether the sides will be battered, which adds volume, and whether the container's weight limit means it cannot be filled.

What bulk factor should I use?

The one for your ground. FM 5-434 (US Army) gives bank-to-loose factors of 1.11 for sand or gravel, 1.25 for loam or common earth, 1.43 for clay and 1.50 for blasted rock, with swell of 10 to 15 percent for sand and gravel, 15 to 35 percent for dry earth and 40 percent for clay. The 1.25 default is the loam figure. Dense clay dug in lumps goes to 1.4 or more; clean sand and gravel bulk least.

Does this tool replace a licensed contractor or engineer?

No. It multiplies the dimensions you give it. How deep an excavation can be dug before it must be supported is a safety matter: in the United States OSHA requires a protective system at 5 ft (1.52 m) unless the ground is stable rock, and in the UK the HSE says no ground can be relied upon to stand unsupported. For work that affects structure, gas, electrics, plumbing or drainage to a public sewer, use a suitably qualified professional.

Can I change the unit prices?

There are no prices on this tool. The editable figures are the dimensions, the bulking factor, the in-place density and the container size; skip hire and tipping are priced by the hirer, usually by the load and by weight, and the load and weight rows are what to give them.